Zone Frontier Inc. (ZONE) Form 8-K — Sep 30, 2026
Zone Frontier Inc. (NYSE American: ZONE) announced that a subsidiary entered into a 30-year Ground Lease with GKC Operating, LLC covering approximately 4,077 acres in Potter County, Texas, securing land, water, and development rights for its West Texas AI data center campus being developed with HST Technologies. Key terms include 200-800 acres designated for data centers with initial capacity of 200 MW and potential beyond 500 MW, at least 1,800 acres for solar and battery storage, base rent that begins only upon construction start, and a purchase option at $100,000-$135,000 per acre for the data center site.
Key figures
- Leased acres
- 4077
- Earnest deposit
- 250000
- Extension options
- two 10-year options
- Revenue share pct
- 0.5
- Initial term years
- 30
- Initial capacity mw
- 200
- Solar site acres min
- 1800
- Potential capacity mw
- 500+
- Data center site acres
- 200-800
- Base rent solar per acre
- 1000
- Base rent data center per acre
- 6000
- Firm service commitment mw min
- 200
- Purchase option per acre pre power
- 100000
- Purchase option per acre post power
- 135000
AI analysis
The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.
AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.