Collective Mining Ltd. (CNL) Form 6-K — Aug 18, 2026
Collective Mining reported that a 1.8-kilometer access road connecting the Pan American Highway to the proposed exploration adit portal at its Guayabales project in Caldas, Colombia is complete, with portal platform and box-cut activities beginning immediately. All required permits are in hand and construction of the exploration adit remains on track to commence in Q4-2026. Underground exploration drilling at the newly identified Trap East greenfield target is scheduled to begin in Q1-2027, marking the start of a program designed to systematically test the Trap system, Apollo's Ramp Zone and Plutus over more than a vertical kilometer from underground.
Key figures
- Best broad intercept
- 632.25 m @ 1.10 g/t AuEq from 172.65 m, incl. 51.50 m @ 2.73 g/t AuEq (TRC-7A, historical)
- Trap vertical extent m
- 900
- Adit construction start
- Q4-2026
- Access road completed km
- 1.8
- Trap main drilling start
- H2-2027
- Best high grade intercept
- 2.80 m @ 234.15 g/t gold from 122.00 m, incl. 0.80 m @ 816 g/t gold (TRC-26, historical)
- Exploration adit length km
- 3
- Underground drilling start
- Q1-2027 (Trap East)
- Current rig extension test m
- 200
- Plutus and ramp zone drilling
- 2028
- Trap corridor strike length km
- 1.4
- Initial extension results expected
- late September
- Insider and aligned ownership percent
- 45.2
- Continental gold sale enterprise value
- approximately $1.4 billion (prior venture of founding team, sold to Zijin Mining)