SILVERCORP METALS INC (SVM) Form 6-K — Nov 3, 2026

$SVMForm 6-KFiled Nov 3, 2026, 5:25 PM ET0001279569-26-001024Original filing

Silvercorp updated the El Domo Project construction budget to $298.2 million, a $14.6 million increase over the February 2026 estimate of $283.6 million and above the original $248 million feasibility figure. Key cost drivers include Ecuador's elimination of diesel subsidies ($8.3M impact), enhanced water management infrastructure ($4.7M), processing plant increases ($3.7M), and new power supply items. Due to heavy rainfall from Super El Nino, the completion date is delayed by four months, with production now expected by November 1, 2027. The company offset $9.8 million through scope reductions including a smaller camp, eliminated water channel, and contingency cuts.

Key figures

Savings million
9.8
Production start
November 1, 2027
Gen set capacity mw
17
Prior budget million
283.6
Schedule delay months
4
Updated budget million
298.2
Budget increase million
14.6
Remaining budget million
213.6
Actual spend sept30 2026 million
84.6
Diesel price increase per gallon
2.7
Feasibility study budget million
248
Package2 mining contract value million
35