Cheniere Energy Partners (CQP) has entered into a $4.69 billion lump-sum turnkey EPC contract with Bechtel Energy for the first phase of its Sabine Pass LNG expansion project. The agreement covers the engineering, procurement, and construction of Train 7 and a boil-off gas re-liquefaction unit, with an expected production capacity of over 6 million tonnes per annum. The company issued a limited notice to proceed on May 22, 2026, allowing Bechtel to commence early engineering and procurement activities.
Key figures
- Deal Value Usd
- 4690000000
- Phase1 capacity mtpa
- 6
- Total expansion capacity mtpa
- 20