Pembina Pipeline Corporation and its partners announced a positive final investment decision on the Greenlight Electricity Centre, a 932 MW gas-fired combined cycle power generation facility to be located in Alberta. The project is backed by a long-term tolling agreement with a major data center customer and is expected to be in-service during the second half of 2030. The total project cost is estimated at approximately $4.6 billion, with Pembina's net investment totaling approximately $2.1 billion after accounting for land sale proceeds.
Key figures
- Project capacity mw
- 932
- Gross capital cost cad
- 4.0B
- Total project cost cad
- 4.6B
- Pembina net investment cad
- 2.1B
- Pembina ownership percent
- 47.5
- Fixed price cost coverage percent
- 85
- Annual run rate adjusted EBITDA cad
- 310M
- Pembina net equity contribution cad
- 1.0B