Fervo Energy Co Form 8-K — Nov 9, 2026

Form 8-KItems 2.02, 7.01, 9.01Filed Nov 9, 2026, 8:37 AM ET0001628280-26-071911Original filing

Fervo Energy reported Q3 2026 results headlined by commercial operation at Cape Station Phase I GeoBlock 1 (33 MW) reached ahead of its contractual date on September 30, with GeoBlocks 2 and 3 on track for commercial operation by January 1, 2027. The company also signed what it believes is the largest enhanced geothermal PPA to date with Google: a 15-year, take-or-pay contract for 396 MW with first power expected mid-2028, plus an option for Google to expand offtake by ~600 MW toward nearly 1 GW total. Binding PPAs now total 1,054 MW representing approximately $11.9 billion in contracted revenue, up from $7.2 billion at the end of Q2.

Key figures

Revenue
$116 thousand (Q3 2026)
Guidance
Q4 2026 capex of $450-500 million; H2 2026 capex of $700-750 million (down from prior $850-900 million); Q4 2026 revenue in line with prior expectations as first full quarter of Cape Station revenue; 2027 revenue outlook unchanged
Total Debt
301600000
Total Assets
3638547000
Cash Position
1900000000
Capex q3
$256.7 million
Google ppa mw
396
Operating loss q3
$43.7 million
Contracted revenue
$11.9 billion
Doe awards potential
$20.0 million
Contracted capacity mw
1054
Geo block 1 capacity mw
33
Capacity in operation mw
36
Google expansion option mw
approximately 600
Cape station hiip potential
8.4 GW (up from 4.3 GW)
Geo block 1 in service cost
$514.3 million transferred to PP&E
Net loss attributable common
$20.8 million
Capacity under construction mw
466
Cape google 400 target cost per kw
$5,500
Installed cost per kw geo blocks 1 3
$7,000

AI analysis

Red flags4 · Pro

The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.

AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.